EPCG Confirms Completion Date for Pljevlja Power Plant Upgrade
The Elektroprivreda Crne Gore (EPCG) has confirmed that the ecological reconstruction project of the Termoelektrana Pljevlja is progressing according to schedule, with the facility set to be operational by November 15, 2025. This announcement comes in response to what EPCG describes as “inaccurate and biased information” circulating in some Montenegrin media regarding timelines and the status of the project.
In its statement, EPCG highlighted that the project commenced in 2020, initially hampered by a contract whose structure and technical documentation contained several deficiencies. To address these issues, EPCG implemented measures to bring the project under full control, enhance technical solutions, and ensure that all work is executed in compliance with the highest European environmental standards.
Progress and Future Plans
According to EPCG, the project is now in its final phase, with construction activities proceeding as planned. The testing phase of the power plant will start on November 15, 2025, lasting several months and involving both hot and cold tests, fine-tuning of systems, and synchronization of all facilities. EPCG emphasized that this timeline does not indicate any delays but rather reflects the technical and legal phases required for commissioning.
The company clarified that any irregularities encountered during construction have been rectified promptly, with increased oversight and active participation from the contractor, the Chinese State Company DEC. The previously reported deadline of September 25 was an internal control date that has been met within the planned framework, negating the need for alternative solutions.
EPCG has also included local and regional subcontractors in the project as per the contractor’s decision, which has further expedited progress without incurring additional costs for the company. The ongoing work is reported to remain within the allocated budget.
Commitment to Stability and Compliance
EPCG firmly rejects allegations suggesting risks of delays or threats to Montenegro’s energy system. They assert that this project is one of the most significant and complex energy initiatives in the country, aimed at ensuring long-term stability and compliance with EU environmental directives.
The company stated, “Individuals and interest groups, who do not align with a stable and successful EPCG, are attempting to downplay the significance of this project.” They reiterated their confidence that such attempts would not succeed.
In conclusion, EPCG affirmed that the project remains fully under control, with construction nearing completion. No contractual deadlines have changed, and November 15 remains the set date for the Termoelektrana Pljevlja to resume operations.
-
Entertainment2 months agoAnn Ming Reflects on ITV’s ‘I Fought the Law’ Drama
-
Entertainment3 months agoKate Garraway Sells £2 Million Home Amid Financial Struggles
-
Health2 months agoKatie Price Faces New Health Concerns After Cancer Symptoms Resurface
-
Entertainment2 months agoCoronation Street’s Carl Webster Faces Trouble with New Affairs
-
Entertainment2 months agoWhere is Tinder Swindler Simon Leviev? Latest Updates Revealed
-
Entertainment3 months agoKim Cattrall Posts Cryptic Message After HBO’s Sequel Cancellation
-
Science3 weeks agoBrian Cox Addresses Claims of Alien Probe in 3I/ATLAS Discovery
-
Entertainment2 months agoOlivia Attwood Opens Up About Fallout with Former Best Friend
-
Entertainment3 months agoMarkiplier Addresses AI Controversy During Livestream Response
-
Entertainment3 months agoMasterChef Faces Turmoil as Tom Kerridge Withdraws from Hosting Role
-
Entertainment4 months agoSpeculation Surrounds Home and Away as Cast Departures Mount
-
World2 months agoCole Palmer’s Mysterious Message to Kobbie Mainoo Sparks Speculation